Over the weekend we finished installing new steam pipes and condensate returns for the brewery boiler. Late Saturday afternoon we fired the boiler up and it seemed to work fine. When we got in Monday to check on things, the sight glass on the brew kettle was broken. We think it probably had the wrong gaskets or some other small problem and cracked during the cool-down. We ordered a replacement, and some valves, and then we're set to start brewing. Later Monday we got our first shipment of brewing ingredients: crushed malt, hops, yeast, and assorted adjuncts and fermentation nutrients. So as soon as we clear up the last little things we will be brewing beer!
Much of the rest of the week was spent in the winery, bottling wine, re-arranging storage, and all kinds of things to get ready for our busiest time of year, the Holiday Season. Later in the week we found out that we still had some major problems with the boiler. Actually, not the boiler, but the configuration of the piping, where and how parts are located, steam condensate traps, pumps, etc. An expert came in and very soon was able to figure out the problems and we ordered some more parts and started what we hope will be our final re-design. Just another week or so and we'll be able to brew.